Saturday 16 June 2012

GROUND FLOOR SLAB - REINFORCEMENT, RADON AND CONCRETE.


Hardcore topping in place and wacking started.
Internal drainage pipes also visible.   


Toilet and soil and vent pipe visible.





Sand blinding progressing.
The main water blue pipe is located at the rear and is located within a lockable box . 





Internal "wet room" drainage system is visible. Shower, toilet, sink and s and vp.








Great place to work !




















Sand blinding layer completed.


Radon barrier and steel mesh reinforcement in place.








Concrete pump on site.


Pump in place - All drainage sealed off.


Concrete wagons arrive.








The start of the concrete pour.












































Floor slab concrete complete.


Concrete pump.