75mm diameter pipe weep holes visible at 900mm centers.
Third coat of waterproofing to rear face of the retaining wall.
B785 vertical mesh progressing to the center of the retaining wall cavity.
Laying of the first course of blockwork for outer skin of the retaining wall.
6 courses of blockwork have been laid.
Concrete is then to be poured within the cavity.
Waterproofing to rear of retaining wall.
The electric meter box location has been constructed into the retaining wall.
No comments:
Post a Comment