Amroth Project
A diary of the regeneration of Ebenezer church in Amroth.
Thursday, 10 May 2012
CONCRETE POURED TO THE RETAINING WALL BASE.
Concrete poured to the new retaining wall base.
The pipe at the rear is the ducted water main connection from the road.
It's great to be out of the ground and moving forward.
Tuesday, 8 May 2012
RETAINING WALL BASE REINFORCEMENT PROGRESS.
A393 mesh top and bottom.
Base a minimum of 300mm thick concrete.
500mm minimum below finished floor level.
Mains water connection ducted through foundation.
Monday, 7 May 2012
SETTING OUT FOR THE RETAINING WALL BASE.
Friday, 27 April 2012
DEMOLITION OF THE BASE OF THE VESTIBULE/PORCH AREA.
Problems over the weekend with the weather.
Roof and one side wall lost.