26th March 2012.
Having found that there is no foundation to the existing front elevation wall and it would collapse when the vestibule is removed, it has been decided, with the help and advise from the Structural Engineer to demolish the existing front elevation and side retaining wall.
An additional planning application has been made for the demolition and re-build of the front elevation and retaining wall.
Productive meeting's have also been made with the Highway's Authority, sewer and main water connection contractor.
Party Wall Act consultation has also been made to both neighbour's.
Road closure and traffic management application's have been made to the Highway Authority.
Hope to start work again after the Easter Bank Holiday.