Monday, 27 February 2012

PROGRESSING SLOWLY INSIDE THE PROPERTY.




Pembrokeshire Council's Beaches Officer is calling today - i have asked if i can just take the old rock/pebbles back to the beach.

MORE WORK TO THE GRAVEYARD STEPS.



MORE EXCAVATIONS FOR THE UNDERPINNING.



The Building Control Officer called today and was happy that we have found rock. The contractor is now going to start work on the preparation of the underpinning.

Tuesday, 21 February 2012

Wednesday, 15 February 2012

STORAGE OF THE FLOOR BOARDS AND A START ON THE NEW ENTRANCE DOOR.



Storing the existing floor boards behind the Chapel to use again.
Ive stored them well off the floor. With a little bit of care they could be nice.




Started to "cut out" the new side entrance door today. Just going to take the inner skin away if i can just to keep the building secure in the mean time.